Ready for an upgrade

The 50-year-old Donald Bridge is scheduled for demolition

by
bridge under construction

Flatiron Constructors of Canada Ltd. started reconstruction of the Donald Bridge in February 2011. — Trevor Crawley photo

As of early May 2012, the Donald Bridge project  25 kilometres west of Golden, B.C., was approximately 65 per cent complete. Flatiron Constructors of Canada Ltd. started reconstruction of 3.5 kilometres of highway and the bridge replacement in February 2011, employing 40 to 60 workers—90 per cent of whom are local. As of mid-April, the workers—including subcontracted labour—had clocked 100,000 hours.

Flatiron project manager Rick Morrison talked about improved safety and traffic flow on both the rebuilt section of highway and the bridge.

“Four lanes will allow better traffic flow,” he said, “and new alignment on the curve allows easier transition through the area.”

The project is scheduled for completion in December 2012.

Marie Milner

Marie Milner is a writer and photographer for Kootenay Business magazine and several other publications. She appreciates the inspiration that she gets during her interviews and hopes to share that inspiration with you. View all of Marie Milner’s articles

Related articles

Business Beat, East Kootenay, Kimberley, Cuisine, Retail, Small Business Good to great: Kimberley’s Grater Good has new owners

Floris and René Steenkamp, new owners of The Grater Good Kitchen Supply Company in Kimberley, B.C., are excited to share their passion for cooking

by
Business Beat, East Kootenay, West Kootenay, Technology, Transportation Regional districts score sustainability award with Accelerate Kootenays project

Three Kootenay regional districts recognized for Accelerate Kootenays initiative

by
Business Beat, East Kootenay, West Kootenay, Education First bilingual youth Science & Tech Program launched in Kootenays by KAST

Celebrating Kootenay biodiversity, the GLOWS program is part of Science Literary Week 2020

by
View all articles

Comments